Key Projects

Always green whenever wherever

Solar - Spain

Under operation

Escuderos – Spain

  • CAPACITY: 200 MW.
  • HOMES POWERED: - GWh. annually
  • CARBON SAVED: 144.690 tonnes over a 40 years
  • LOCATION: Poveda de la Obispalía, Spain
  • DATE: 2024
View project

Pipeline stages

Different projects in development, ready to build or at different stages of maturity.

20 - 40%

Identified Opportunities

A project that is technically and financially feasible, given that: the possibility of land exists, access to the electricity grid is operationally feasible, and/or the possibility of selling to third parties also exists.

50%

Early stage

A project that is technically and financially feasible, given that: the possibility of land exists, access to the electricity grid is operationally feasible, and/or the possibility of selling to third parties also exists.

70%

Advanced development

A project is advanced when land is secured (>50% chance) and grid access approval is likely (>90%). It is pre-construction when land, grid access, and environmental approval (>90%) are secured, with a PPA or equivalent agreement ready to sign.

90%

Backlog

Project in its final stages prior to construction, where: the land and access to the electricity grid are guaranteed, the probability of the environmental permit being approved is more than 90%, and there is a PPA in place; or a framework contract with an off taker or bank ready to be signed; or a bankable price stabilization scheme.

100%

Under construction

The EPC constructor has been given the order to start building.

100%

IPP operation

Project acceptance has been signed. Responsibility for the asset has been transferred from the constructor to the operations team.