Key Projects

Greenbox Projects

Oviedo – Greenbox

View project

Oviedo, 33011 Municipality of Oviedo, Asturias, Spain

43°23`N 5°50´W

Operating since

2027

Storage

CountriesSolar (MW)Storage (MWh)Hybridization (MWh)
Spain1,350 MW6,445 MWh3,280 MWh
Italy507 MW7,119 MWh1,500 MWh
United Kingdom176 MW4,439 MWh460 MWh
Germany401 MW1,559 MWh0 MWh
Chile5,799 MW0 MWh26,053 MWh
Colombia241 MW0 MWh0 MWh
Mexico762 MW0 MWh620 MWh
Peru1,726 MW0 MWh3,888 MWh
United States1,314 MW2,745 MWh2,025 MWh
Poland0 MW4,803 MWh0 MWh
Romania0 MW5,535 MWh0 MWh
Total12,276 MW32,645 MWh37,826 MWh

Pipeline stages

Different projects in development, ready to build or at different stages of maturity.

20 - 40%

Identified Opportunities

A project that is technically and financially feasible, given that: the possibility of land exists, access to the electricity grid is operationally feasible, and/or the possibility of selling to third parties also exists.

50%

Early stage

A project that is technically and financially feasible, given that: the possibility of land exists, access to the electricity grid is operationally feasible, and/or the possibility of selling to third parties also exists.

70%

Advanced development

A project is advanced when land is secured (>50% chance) and grid access approval is likely (>90%). It is pre-construction when land, grid access, and environmental approval (>90%) are secured, with a PPA or equivalent agreement ready to sign.

90%

Backlog

Project in its final stages prior to construction, where: the land and access to the electricity grid are guaranteed, the probability of the environmental permit being approved is more than 90%, and there is a PPA in place; or a framework contract with an off taker or bank ready to be signed; or a bankable price stabilization scheme.

100%

Under construction

The EPC constructor has been given the order to start building.

100%

IPP operation

Project acceptance has been signed. Responsibility for the asset has been transferred from the constructor to the operations team.

Always green whenever wherever

Hybridization - Spain

Under operation

Escuderos

  • CAPACITY: 200 MW.
  • HOMES POWERED: - GWh. annually
  • CARBON SAVED: 144.690 tonnes over a 40 years
  • LOCATION: Poveda de la Obispalía, Spain
  • DATE: 2024
View project