Wold Newton - BESS

Headquarters

12th Floor, 5 Merchant Square, London, W2 1AY

51°31`N 0°5´W

Grenergy is proposing to build a 30MW Battery Energy Storage System at Gunnerby Farm, Hatcliffe, DN37 0SP

About the project

This project will provide crucial services to the local electricity distribution network to ensure the supply of clean and cost-effective electricity to domestic, commercial and industrial users of the electricity network.

As the UK shifts towards more renewable energy sources, like solar and wind, BESS sites enable energy from renewables to be stored and then released when the power is needed most.

The UK government estimates technologies like battery storage systems, supporting the integration of more low-carbon power and reducing the carbon and cost impact of running the electricity network, could save the UK energy system up to £40 billion by 2050.

Key Features

30MW Storage Capacity
Capable of storing and discharging electricity to meet both local and national demand.

Strategic Connection
Direct connection into the Wold Newton Substation located immediately to the south of the site.

Low Visual Impact
Designed with minimal visual intrusion, incorporating screening and strategic landscaping where necessary.

Green Energy Support
The BESS will play a vital role in integrating renewable energy into the grid, reducing dependence on non-renewable sources.

Our Projects

Storage - United Kingdom

Advanced development

Wold Newton

  • CAPACITY: 30 MW.
  • HOMES POWERED: - GWh. annually
  • CARBON SAVED: - tonnes over a 40 years
  • LOCATION: Gunnerby Farm, Grimsby DN37 0SP, UK
  • DATE: 2024
View project

Indicative Timeline for Hatcliffe BESS

Q4 2024

Project Secured with Grid

Capacity to connect project into the grid network secured with Distribution Network Operator

Q2 2025

Planning Submitted

Application to North East Lincolnshire Council for full planning consent for a Battery Energy Storage System

Q4 2025

Planning Decision

Planning permission granted subject to conditions

Q4 2026

Pre-construction works

Subject to consent granted, contracts secured, consents obtained and land agreements triggered

Q1 2027

Construction starts

Site mobilisation for construction works to begin

Q4 2027

Provisional Operation Date

Operational date subject to network upgrade works from the local and national network operators

Structure of a BESS plant

FAQs

We use Battery Energy Storage Systems (BESS) to store renewable energy, such as solar and wind, and release it when power is most needed. While their primary function is to capture surplus clean electricity and discharge it later, they also provide essential grid stability services. For example, they help us manage voltage and frequency imbalances caused by fluctuations in renewable energy generation.

Across the UK, we lose large amounts of renewable energy, like wind and solar, when we cannot immediately use it because we lack sufficient storage capacity. To meet the UK’s net-zero goals and reduce dependency on fossil fuels, it is essential to expand BESS capacity. Battery energy storage systems ensure a stable and efficient electricity supply, especially during the transition to renewable sources. By storing energy when production is high and releasing it when demand increases, they help balance the grid, reduce CO₂ emissions, and minimize operational costs. Additionally, they enhance the resilience of the electrical system, providing backup during critical moments and facilitating the secure integration of solar and wind energy, ensuring a more sustainable energy future.

The batteries themselves produce very little noise, however, cooling fans are required to maintain the batteries at the correct temperature which emit some noise. With any planning application a detailed Noise Assessment is completed to ensure the plant causes no detriment to local sound levels.

Once planning consent is secured and we have the green-light from National Grid to proceed, then construction typically takes 9 months. The scheme would have an operational lifespan of 30 years before a decommissioning period of around 6 months, when the site will be returned to its previous use.

We are committed to minimizing traffic impacts during the construction period through careful route planning and traffic management. Once the site becomes operational, traffic will reduce significantly, averaging only 1–2 vans per week. A full Construction Transport Management Plan will accompany our planning application.

BESS sites are under frequent scrutiny regarding fire safety, due to the large quantities of lithium-ion batteries in a confined space. Fire mitigation is therefore at the forefront of considerations at all sites like this one. The National Fire Chiefs Council provide the following advice to all developers of BESS sites. The summary of fire safety measures are as follows:

  • Engagement with local fire authority and planning authority with emergency response plans, fire water management strategies and fire safety management plans
  • Separation distances or thermal barriers between all equipment, including the battery containers
  • Fire detection, monitoring and prevention systems installed within all battery modules
  • Sufficient ventilation (cooling fans) to maintain temperatures for all potential scenarios
  • Water supply – onsite to meet the demand of the local fire authority, e.g. hydrants or water tanks
  • Multiple access routes and space within compounds to ensure fire engines have access to and within the site

Grenergy have taken all advice on-board to produce a design which aligns with this guidance and is detailed in the documents submitted with the full planning application.

We are dedicated to increasing biodiversity through the planting of native species, including wildflowers, hedgerow restoration, and woodland creation, all aimed at supporting local wildlife and habitats. In addition, we offer community benefits that will directly support local causes and organizations, ensuring meaningful investment in the community.

Downloads

12 Jun 2025

PDF — 420.16 KB

28 Apr 2025

PDF — 859.56 KB

01 May 2025

PDF — 3.42 MB