
Storage - United Kingdom
Advanced development
Salt Way
- CAPACITY: 70 MW.
- HOMES POWERED: - GWh. annually
- CARBON SAVED: - tonnes over a 40 years
- LOCATION: Redditch B96 6JT, UK
- DATE: 2024
Headquarters
12th Floor, 5 Merchant Square, London, W2 1AY
51°31`N 0°5´W
Emails
Phones
Grenergy is proposing to build a 70MW Battery Energy Storage System in Feckenham, Worcestershire, B96 6JT
The facility will provide critical energy storage infrastructure, supporting the transition to renewable energy by storing excess electricity and releasing it when demand is high. This project is part of the UK’s efforts to stabilize the energy grid, reduce reliance on fossil fuels, and help achieve Net Zero targets. The site’s rural location provides natural buffering, minimising potential visual and noise impacts on surrounding communities.
The UK government estimates technologies like battery storage systems, supporting the integration of more low-carbon power and reducing the carbon and cost impact of running the electricity network, could save the UK energy system up to £40 billion by 2050.
70MW Storage Capacity
Capable of storing and discharging electricity to meet both local and national demand.
Strategic Connection
Connecting into the Feckenham Substation through an underground 132kV cable. The close proximity to the substation means less disruption to the local road network.
Located Outside the Green Belt
The site is situated beyond designated Green Belt land, ensuring that the development does not impact protected open spaces or restrict future growth in constrained areas.
Low Visual Impact
Designed with minimal visual intrusion, incorporating screening and strategic landscaping where necessary.
Green Energy Support
The BESS will play a vital role in integrating renewable energy into the grid, reducing dependence on non-renewable sources.
Storage - United Kingdom
Advanced development
We use Battery Energy Storage Systems (BESS) to store renewable energy, such as solar and wind, and release it when power is most needed. While their primary function is to capture surplus clean electricity and discharge it later, they also provide essential grid stability services. For example, they help us manage voltage and frequency imbalances caused by fluctuations in renewable energy generation.
Across the UK, we lose large amounts of renewable energy, like wind and solar, when we cannot immediately use it because we lack sufficient storage capacity. To meet the UK’s net-zero goals and reduce dependency on fossil fuels, it is essential to expand BESS capacity. Battery energy storage systems ensure a stable and efficient electricity supply, especially during the transition to renewable sources. By storing energy when production is high and releasing it when demand increases, they help balance the grid, reduce CO₂ emissions, and minimize operational costs. Additionally, they enhance the resilience of the electrical system, providing backup during critical moments and facilitating the secure integration of solar and wind energy, ensuring a more sustainable energy future.
BESS sites are under frequent scrutiny regarding fire safety, due to the large quantities of lithium-ion batteries in a confined space. Fire mitigation is therefore at the forefront of considerations at all sites like this one. The National Fire Chiefs Council provide the following advice to all developers of BESS sites. The summary of fire safety measures are as follows:
Grenergy have taken all advice on-board to produce a design which aligns with this guidance and is detailed in the documents submitted with the full planning application.
We are dedicated to increasing biodiversity through the planting of native species, including wildflowers, hedgerow restoration, and woodland creation, all aimed at supporting local wildlife and habitats. In addition, we offer community benefits that will directly support local causes and organizations, ensuring meaningful investment in the community.
The batteries themselves produce very little noise, however, cooling fans are required to maintain the batteries at the correct temperature which emit some noise. With any planning application a detailed Noise Assessment is completed to ensure the plant causes no detriment to local sound levels.
We are committed to minimizing traffic impacts during the construction period through careful route planning and traffic management. Once the site becomes operational, traffic will reduce significantly, averaging only 1–2 vans per week. A full Construction Transport Management Plan will accompany our planning application.
Once planning consent is secured and we have the green-light from National Grid to proceed, then construction typically takes 9 months. The scheme would have an operational lifespan of 30 years before a decommissioning period of around 6 months, when the site will be returned to its previous use.